彭华, 杨志蔚, 曹全, 马文辉. 盾构下穿铁路碎石道床沉降规律及施工参数控制[J]. 工程力学, 2019, 36(S1): 222-228. DOI: 10.6052/j.issn.1000-4750.2018.04.S044
引用本文: 彭华, 杨志蔚, 曹全, 马文辉. 盾构下穿铁路碎石道床沉降规律及施工参数控制[J]. 工程力学, 2019, 36(S1): 222-228. DOI: 10.6052/j.issn.1000-4750.2018.04.S044
PENG Hua, YANG Zhi-wei, CAO Quan, MA Wen-hui. THE SETTLEMENT LAW OF RAILWAY BALLAST BEDS TRAVERSED BY A SHIELD TUNNEL AND THE CONTROL OF SHIELD CONSTRUCTION PARAMETERS[J]. Engineering Mechanics, 2019, 36(S1): 222-228. DOI: 10.6052/j.issn.1000-4750.2018.04.S044
Citation: PENG Hua, YANG Zhi-wei, CAO Quan, MA Wen-hui. THE SETTLEMENT LAW OF RAILWAY BALLAST BEDS TRAVERSED BY A SHIELD TUNNEL AND THE CONTROL OF SHIELD CONSTRUCTION PARAMETERS[J]. Engineering Mechanics, 2019, 36(S1): 222-228. DOI: 10.6052/j.issn.1000-4750.2018.04.S044

盾构下穿铁路碎石道床沉降规律及施工参数控制

THE SETTLEMENT LAW OF RAILWAY BALLAST BEDS TRAVERSED BY A SHIELD TUNNEL AND THE CONTROL OF SHIELD CONSTRUCTION PARAMETERS

  • 摘要: 为研究盾构下穿施工影响下铁路碎石道床的沉降规律以及控制道床沉降的盾构施工参数调控要点,以北京岳各庄电力工程盾构隧道下穿京广铁路工程为例,通过数值模拟、现场实测分析了盾构下穿施工中道床沉降的时程变化规律及沉降槽发展趋势,继而结合对盾构施工参数的分析,探究了沉降规律与盾构施工参数的关系。研究结果表明: 1)碎石道床沉降的数值模拟结果与监测数据有一致性,由于在下穿施工中盾构施工参数的调控较为严格,故道床沉降速率缓和,而在下穿施工前后道床沉降速率较快; 2)通过对盾构施工参数的调控,可以有效地控制道床的沉降。下穿施工中,盾构出土量均值控制在18.8 m3,约为理论出土量的1.25倍;土仓压力保持平稳增长,由0.050 MPa逐步增大至0.054 MPa;扭矩值控制在了1150 kN/m~1200 kN/m;同步注浆量与二次注浆量也配合着土仓压力的变化而及时增减。

     

    Abstract: To study the settlement law and the key points of construction parameters of shield tunnels for controlling the subsidence of ballast beds caused by traversing construction of shield tunnels, based on the Beijing power transmission project of the cable shield tunnel beneath the Beijing-Guangzhou railway, the time course change and development trend of the settlement trough during the shield construction was analyzed using finite element numerical simulation and monitoring. A thorough investigation of the law of railway settlement and the control of shield construction parameters is conducted by analyzing shield construction parameters. The results indicates:1) The numerical model results of the subsidence of ballast bed and monitoring data have good consistency, and the subsidence of ballast bed was moderate due to a strict control of the shield construction parameters during the traversing process while a high rate in the prophase and later period was present; 2) The subsidence of railway could be effectively controlled by controlling the construction parameters of the shield tunnel. During the construction, the average value of shield excavation was controlled to be approximately 18.8 m3, which is approximately 1.25 times of the theoretical value. The pressure of the soil chamber maintained steady growth from 0.050 MPa to 0.054 MPa. The torque value was well controlled at 1150 kN/m-1200 kN/m. The synchronous grouting and secondary grouting cooperated well with the change of the pressure of the soil chamber through timely increase or decrease.

     

/

返回文章
返回