  • For casting in-site concrete buildings during construction, the dead loads of newly poured concrete slab and construction live loads are carried by time-dependent structures, which consist of early-age concrete structures and formwork system. The lack of understanding of the properties and design and analysis method for reinforced concrete buildings during construction results in high rate of quality problem and collapse during construction than that in service. Based on the concept that early-age concrete structures are the early-time form of building design production, which cannot be changed with construction progress, a design and analysis method for reinforced concrete structures during construction is proposed. Statistical parameters of construction error of formworks and construction loads are suggested based on site measurement, and examples are presented.
  • Related Articles

    [1]FAN Wen-liang, LIU Cheng, LI Zheng-liang. IMPROVED RELIABILITY METHOD BASED ON HLRF AND MODIFIED SYMMETRIC RANK 1 METHOD[J]. Engineering Mechanics, 2022, 39(9): 1-9. DOI: 10.6052/j.issn.1000-4750.2021.05.0379
    [2]JIN Lu, MA Yun-si, LIU Dan. ANALYSIS METHODS FOR SECOND-ORDER DRIFT OF BRACE-STEEL FRAME STRUCTURE[J]. Engineering Mechanics, 2019, 36(S1): 194-198,216. DOI: 10.6052/j.issn.1000-4750.2018.05.S039
    [3]HUANG Xiao-ning, WANG Ning, DU Yong-feng. RELIABILITY ANALYSIS OF THE VERTICAL PROGRESSIVE COLLAPSE OF BASE-ISOLATED FRAME-WALL STRUCTURES UNDER EARTHQUAKES[J]. Engineering Mechanics, 2019, 36(9): 89-94,127. DOI: 10.6052/j.issn.1000-4750.2018.07.0389
    [4]LI Zheng-liang, ZU Yun-fei, FAN Wen-liang, ZHOU Qing-yu. RELIABILITY ANALYSIS OF MULTI-COMPONENTS IN STRUCTURAL SYSTEM BASED ON THE ADAPTIVE POINT ESTIMATE METHOD AND THE PRINCIPLE OF MAXIMUM ENTROPY[J]. Engineering Mechanics, 2019, 36(5): 166-175. DOI: 10.6052/j.issn.1000-4750.2018.04.0223
    [5]MENG Zeng, LI Gang. MODIFIED CHAOS CONTROL-BASED FIRST ORDER SECOND MOMENT RELIABILITY METHOD[J]. Engineering Mechanics, 2015, 32(12): 21-26. DOI: 10.6052/j.issn.1000-4750.2014.05.0360
    [6]BAI Bing, ZHANG Qing-hua, LI Qiao. REGRESSION ANALYSIS-PREDICTION ALGORITHM FOR STRUCTURAL SECOND-ORDER SECOND-MONMENT RELIABILITY INDEX EVALUATION[J]. Engineering Mechanics, 2013, 30(10): 219-226,235. DOI: 10.6052/j.issn.1000-4750.2012.07.0501
    [7]YANG Jie, ZHANG Qi, HUANG Yi. A NEW SENSITIVITY FACTOR FOR STRUCTURAL RELIABILITY[J]. Engineering Mechanics, 2013, 30(6): 16-21. DOI: 10.6052/j.issn.1000-4750.2012.02.0088
    [8]JIANG You-bao, LIU Yang, ZHANG Jian-ren. COMPUTATIONAL METHOD OF SYSTEM RELIABILITY BASED ON CHARACTERISTICS OF FAILURE BOUNDARY[J]. Engineering Mechanics, 2010, 27(8): 77-082.
    [9]XIONG Tie-hua, CHANG Xiao-lin. APPLICATION OF RESPONSE SURFACE METHOD IN SYSTEM RELIABILITY ANALYSIS[J]. Engineering Mechanics, 2006, 23(4): 58-61.
    [10]Liu Xiaoqiang, Wu Huibi. APPROXIMATE DESIGN METHOD FOR SECOND ORDER EFFECT IN HIGHRISE FRAMEWORKS[J]. Engineering Mechanics, 1993, 10(2): 72-78.

Catalog

    Article Metrics

    Article views PDF downloads Cited by()
    Related

    /

    DownLoad:  Full-Size Img  PowerPoint
    Return
    Return