XIONG Xue-yu, GU Wei. LONG-TERM PERFORMANCE PROBABILISTIC ANALYSIS OF PC STRUCTURE BASED ON IMPROVED LHS METHOD[J]. Engineering Mechanics, 2010, 27(4): 163-168.
Citation: XIONG Xue-yu, GU Wei. LONG-TERM PERFORMANCE PROBABILISTIC ANALYSIS OF PC STRUCTURE BASED ON IMPROVED LHS METHOD[J]. Engineering Mechanics, 2010, 27(4): 163-168.

LONG-TERM PERFORMANCE PROBABILISTIC ANALYSIS OF PC STRUCTURE BASED ON IMPROVED LHS METHOD

More Information
  • Received Date: December 31, 1899
  • Revised Date: December 31, 1899
  • The sample point generation strategy used in Latin Hypercube Sampling Monte-Carlo method is improved in according with the large variability of a concrete shrinkage and creep model. The improved strategy is developed under an unbiased mean value restriction; it can avoid negative values of random variables, so as to conform to the physical meaning. A simple example of shrinkage strain calculation shows that the improved strategy has an identical mean value and a slightly decreased standard deviation comparing to unimproved one. The probabilistic analysis is performed for a super long prestressed concrete frame structure; the changes of side column displacements and slab stresses in 10000 days are studied. The results prove that the improved sampling strategy can be applied successfully in the long-term performance probabilistic analysis for large and complex structures.
  • Related Articles

    [1]DENG Ji-hua, SHAO Xu-dong, TAN Ping. FINITE ELEMENT ANALYSIS FOR 3-D FRAME STRUCTURES UNDER COMBINED ACTIONS OF GEOMETRIC NONLINEARITY AND CREEP[J]. Engineering Mechanics, 2015, 32(6): 117-123. DOI: 10.6052/j.issn.1000-4750.2013.12.1127
    [2]PAN Zuan-feng, LU Zhi-tao, LIU Zhao, MENG Shao-ping. UNCERTAINTY ANALYSIS OF CREEP AND SHRINKAGE EFFECT IN CONTINUOUS RIGID FRAME OF SUTONG BRIDGE[J]. Engineering Mechanics, 2009, 26(9): 67-073.
    [3]FANG Hui, SHEN Pu-sheng. ANALYSIS OF HIGH-RISE FRAME STRUCTURES WITH CONSTRUCTION PROCESS, CREEP AND SHRINKAGE EFFECTS[J]. Engineering Mechanics, 2007, 24(7): 94-098,.
    [4]XI Hai-feng, FANG Dong-ping, ZHANG Chuan-min, GENG Chuan-dong. CREEP EFFECTS ON LOAD DISTRIBUTION OF REINFORCED CONCRETE STRUCTURES DURING CONSTRUCTION[J]. Engineering Mechanics, 2007, 24(3): 91-096.
    [5]HU Di. THE PRECISION-CONTROLLABLE GENERAL APPROACH TO ANALYZE TIME-DEPENDENT EFFECT IN PRESTRESSED CONCRETE STRUCTURES[J]. Engineering Mechanics, 2006, 23(12): 117-122.
    [6]LUO Xu-guo, ZHONG Xin-gu, DAI Gong-lian. EXPERIMENTAL STUDY ON THE DEFORMATIONS FOR SHRINKAGE AND CREEP OF BEAMS IN NON-GLUED PRESTRESSED HIGH PERFORMANCE FLY ASH CONCRETE BRIDGES[J]. Engineering Mechanics, 2006, 23(7): 136-141.
    [7]HU Di. THE STEEL RESTRAINT INFLUENCE COEFFICIENT METHOD TO ANALYZE TIME-DEPENDENT EFFECT IN PRESTRESSED CONCRETE BRIDGES[J]. Engineering Mechanics, 2006, 23(6): 120-126.
    [8]XIANG Tian-yu, TONG Yu-qiang, ZHAO Ren-da. CREEP ANALYSIS OF CONCRETE STRUCTURE BY DEGENERATED BEAM ELEMENT[J]. Engineering Mechanics, 2006, 23(4): 140-143.
    [9]HU Di, CHEN Zheng-qing. AUTOMATICALLY STEP-UP METHOD FOR CREEP ANALYSIS OF PRESTRESSED CONCRETE BRIDGES[J]. Engineering Mechanics, 2004, 21(5): 41-45,7.
    [10]QIU Wen-liang, JIANG Meng, ZHANG Zhe. FINITE ELEMENT ANALYSIS OF CREEP AND SHRINKAGE OF STEEL-CONCRETE COMPOSITE BEAMS[J]. Engineering Mechanics, 2004, 21(4): 162-166.

Catalog

    Article Metrics

    Article views (1418) PDF downloads (447) Cited by()